- Best Practices for Equipment O&M
-
O&M Best Practice Issue Discussions
- Advanced Maintenance Approach: Reliability Centered Maintenance
- Applying Key Performance Indicators
- Comprehensive O&M Program
- Contract Challenges and Improvements
- Cybersecurity for O&M Systems
- Existing Building Commissioning Procurement
- Healthy Building O&M
- Integrating and Analyzing Building Information to Support O&M
- Maintenance Approaches
- OMETA: An Integrated Approach to Operations, Maintenance, Engineering, Training, and Administration
- Prioritizing O&M Actions
- Re-tuning Buildings
- O&M Contracting
- Tools
- Glossary
Introduction to O&M Contract Tool
Introduction
The Technical Specifications for Contract Language for Operations and Maintenance (O&M) Services are designed to help federal agencies create contract language suitable for inclusion in existing and proposed O&M contracts. The templates, to be customized by the agency (see brackets with words highlighted in yellow), can be found here: O&M Contracts Templates.
These customizable templates focus on supplementing existing (or proposed) contracts, enabling the development of site-specific prescriptive or performance-based O&M contract language.
Provided templates are not designed to generate or replace the complete O&M contract, nor do they address the legal or logistical elements of the contract—those sections are best prepared by each agency’s contracting officer (CO), often with support of a contract specialist (CS). Rather, each customizable template provides the language to be inserted into the technical service contract or statement of work (SOW) sections of the larger O&M contract.
The customizable templates are intended to:
- Reduce the time, complexity, and level of effort by offering technology-specific best practices to improve the development of an O&M services contract.
- Provide comprehensive (and customizable) contract language designed to be adaptable to specific agency, site, equipment, and facility O&M needs. This will consider legislative requirements while providing a documented (metrics-based) path to the O&M aspects of energy and water efficiency, as well as improved system resilience, availability, and reliability.
Statements of Work/Performance Work Statements
As described in O&M Contract Guidance and Best Practices, an O&M contract can come in several different forms and formats. While different in appearance, many O&M contracts contain similar sections, content, requirements, and references. The downloadable templates are primarily intended to interface with the SOW or the “Performance Work Statement” element of the overall O&M contract. The SOW content, usually found in Section C of Part I of the overall contract, delineates the scope of the O&M services and administrative aspects of the contract.
A standard outline of Section C will often include (GSA 2022; U.S. Army 2009):
- Section C-1: General Information
- Section C-2: Definitions
- Section C-3: Government-Furnished Property and Services
- Section C-4: Contractor-Furnished Items
- Section C-5: Operations-Specific Requirements
- Section C-6: Maintenance-Specific Requirements
- Section C-7: Administrative Instructions
- Section C-8: Publications, Technical Exhibits, and Cited Standards
Depending on the structure, the equipment-specific contract language will usually be found in Section C-6: Maintenance-Specific Requirements.
Contracting Approaches to Maintenance-Specific Requirements
Provided templates contain SOW contract language for technical O&M processes and procedures at the system, equipment, and/or component levels for eight example technologies. For each technology, O&M specifications are provided for two maintenance approaches: prescriptive-based or performance-based.
Prescriptive-based O&M Contract. This more traditional approach requires a contractor to follow a well-defined and standardized set of actions and/or procedures at specified frequencies as explained in the contract. A prescriptive approach will often use standardized checklists that the contractor follows at specified intervals (regardless of need).
This approach can maintain the equipment’s warranty and help extend its useful life when the manufacturer’s prescribed maintenance schedule is followed. However, it can also result in unnecessary maintenance activities, inefficient use of staff time and resources, and limited innovation because it does not fully leverage the contractor’s expertise or encourage process improvements.
Performance-based O&M Contract. This approach focuses on desired outcomes or results rather than specific procedures. It gives the contractor flexibility in determining how to achieve the required performance. Under this model, the customer contracts for specific services and measurable outcomes, not resources. As such, the contractor flexibility is increased, customer oversight is decreased, and management attention shifts toward results and performance.
In the performance-based approach, the SOW contains explicit, measurable performance requirements (e.g., metrics; the “what”), eliminates process-oriented requirements (the “how”), and includes only minimally essential reporting requirements that are based on risk. The agency employs a measurement and verification method that is clearly communicated to the contractor and where the contractor is held fully accountable using key performance indicators as shown in section IX, Key Performance Indicators and Metrics.
However, performance-based contracts are complex to draft, can involve higher monitoring costs, and may increase the risk of contractor disputes. The advantages and disadvantages of both contract types must be carefully considered when choosing an O&M approach. Aspects of each approach are summarized in Table A.
Table A. Comparison of O&M Contract Approaches
Aspect | Prescriptive-Based O&M Contract | Performance-Based Contract |
| Core Philosophy | Specifies how the work must be performed (detailed procedures and frequencies) | Specifies what results/outcomes must be achieved (focus on performance metrics) |
| Contractor Role | Follows standardized checklists and fixed schedules, regardless of actual need | Gives flexibility to determine methods, leveraging expertise and innovation |
| Customer Oversight | Provides higher insight: monitors adherence to prescribed steps | Offers lower insight: focuses on verifying results rather than processes |
| Warranty & Equipment Life | Strong protection when manufacturer’s prescribed maintenance is followed | Depends on contractor’s ability to meet performance standards; may require additional verification |
| Efficiency & Cost | Can result in unnecessary maintenance and inefficient use of resources | Can reduce overall costs by avoiding unneeded work and enabling innovative solutions |
| Innovation | Allows for limited innovation—contractor follows fixed procedures | Encourages innovation—contractor can propose and apply better methods |
| Complexity | Simpler to draft and administer | More complex to draft, measure, and verify |
| Risks | Wasted activities, poor use of staff time, missed opportunities for improvement | Higher monitoring costs, potential contractor dispute, risk of unclear metrics |
| Best Suited For | Equipment with strict warranty requirements, regulatory compliance, or low-risk/standard assets | Mature programs where outcomes can be clearly defined and measured |
The contract templates provided for both prescriptive and performance approaches also allow for a hybrid approach, which combines prescriptive and performance mechanisms. For example, contracts can be very specific (and prescriptive) with certain systems (e.g., high-reliability and/or sensitive equipment) while a performance-based approach can be selected for systems not needing such specificity and prescription.
Key Performance Indicators
In addition to contract language templates, key performance indicators (KPIs) are included for each example technology. Developing and applying KPIs is a valuable way for building owners, contractors, and their O&M organizations to measure performance and identify areas in need of improvement.
In general, a KPI can be defined as a numeric value used to measure and evaluate the progress toward a defined goal or objective. KPIs are typically generated by combining one or more relevant values into a mathematical relationship to express the performance, condition, or efficiency of a part, system, facility, or organization (PNNL 2021).
KPIs span the topic areas of planning, scheduling, execution, reliability, response, organization, cost, performance, and safety, among others. KPIs fall into one of two distinguishing categories: a leading KPI or a lagging KPI.
- A leading KPI is usually process-specific and is a measure of performance prior to change or degradation. Leading KPIs are used most often to track and define future progress and success. An example of a leading KPI is the percentage of maintenance work orders requiring rework.
- A lagging KPI is a measure of what has already happened and how it impacts the system, process, or business. Lagging KPIs provide an indication of past success or deficiency. An example of a lagging KPI is the mean time between failure.
The tables below are organized to span the range from generic KPIs (relevant to cross-site application) to technology-specific KPIs that are relevant to only the technology presented.
To make full use of KPIs, some reference or target needs to be developed or provided. These references or targets are often referred to as metrics or benchmarks. Metrics and benchmarks can be presented as target values but are often presented as ranges or percentages. The third column in the tables below highlights the reference metrics for each KPI (PNNL 2021).
When developing the scope of work, these KPIs can be reviewed and considered for inclusion in the contract language.
Table B. High-Level Site-Wide/Facility Specific KPIs and Metrics
Site-Wide or Facility-Specific | ||
Area | KPI | Target Metric |
| Energy Use | Energy Use Intensity (EUI): Annual total energy use over relevant conditioned square footage (1) | Site-specific, within targeted range |
| Energy Star Portfolio Manager Score (1) | Site-specific, within targeted range | |
Area | KPI | Target Metric |
| Water Use | Water Use Intensity (WUI): Annual total water-use over relevant square footage (2) | Site-specific, within targeted range |
Area | KPI | Target Metric |
| Greenhouse Gas | GHG Emissions Generated: Annual total GHG, equivalency of CO2 metric tons (3), plus other? | Site-specific, within targeted range |
Area | KPI | Target Metric |
| Occupant Related | Hot Calls: Occupant calls totaled over time interval (month, quarter, year) | Site-specific, within targeted range |
Cold Calls: Occupant calls totaled over time interval (month, quarter, year) | Site-specific, within targeted range | |
| Satisfaction Rating: Occupant complaints totaled over time interval (month, quarter, year) | Site-specific, within targeted range | |
| Notes: Add: (1) Reference EUI definition. (2) Reference WUI definition. (3) Reference GHG requirements | ||
Table C. O&M Program Leading KPIs and Metrics
Leading KPIs | ||
Area | KPI | Target Metric |
| Work Planning | Planned Downtime: Planned or scheduled downtime or shutdown over total uptime | Target <10%, trending downward |
Area | KPI | Target Metric |
| Work Execution | Schedule: Work orders (total number) with defined schedule | Target >95%, trending upward |
Backlog Percentage: Work orders in backlog status over total work orders | Target <5%, trending downward | |
Rework Percentage: Percentage of work orders in rework status; work orders in rework status over total work orders | Target <3%, trending downward | |
Area | KPI | Target Metric |
| Work Administration | Training: Number of training events or days/hours over number of staff | Industry specific, trending upward |
Proficiency: Staff carrying certification over total number of staff | Industry specific, trending upward | |
Table D. O&M Program Lagging KPIs and Metrics
Lagging KPIs | ||
Area | KPI | Target Metric |
| Equipment Effectiveness | Availability: Equipment uptime over expected operating time including planned downtime | Target >90%, trending upward |
Downtime: Unplanned equipment failures/shutdowns over planned equipment failures/shutdowns | Target >90%, trending upward | |
Mean Time Between Failure: Total operating time over number of failures | Industry/system specific, trending upward | |
Occupant Satisfaction: Occupant complaints totaled over time interval (month, quarter, year) | Industry specific, trending downward | |
Occupant Satisfaction: Occupant complaints totaled over time interval (month, quarter, year) | Industry specific, trending downward | |
Area | KPI | Target Metric |
| Maintenance Cost/Financial Effectiveness | Maintenance Cost: Total maintenance cost over cost of previous year/s | Industry specific, trending downward |
Facility Condition: Total maintenance cost over replacement asset value of equipment | Target <3%, trending downward | |
Area | KPI | Target Metric |
| Programmatic Effectiveness | Corrective Maintenance: Corrective maintenance hours over total maintenance hours | Target <10% to 20%, trending downward |
Preventive Maintenance: Preventive maintenance hours over total maintenance hours | Target >25% to 35%, trending steady to upward | |
Condition-based/Predictive Maintenance: Predictive maintenance hours over total maintenance hours | Target >45% to 55%, trending upward | |
Area | KPI | Target Metric |
| Safety and Environment Effectiveness | Safety Severity: Hours lost to injuries for maintenance personnel over total hours worked by maintenance personnel | Industry specific, trending downward |
Environmental Effectiveness: Number of reportable environmental events over total hours worked by maintenance personnel | Industry specific, trending downward | |
Conclusions and Next Steps
The collection of downloadable templates offers O&M specifications for both prescriptive-based paths (traditional O&M activities following well-defined actions and frequencies) and performance‑based paths (a contemporary O&M approach relying on outcome-based performance activities with definable metrics).
Additionally, these specifications can be combined into a hybrid approach using specifications from both prescriptive and performance paths to meet unique equipment needs. Coupled with each technology is a metric and key-performance indicator table. These tables offer a selection of editable metrics providing options to track contractor activity and performance.
The contract language and KPI metrics can be implemented into the technical service contract or SOW sections of the larger O&M contract. For additional information on O&M contracts, see O&M Contract Guidance and Best Practices.
O&M contract templates can be downloaded at O&M Contracts Templates.
IMPORTANT: The downloadable templates contain highlighted words {in brackets} that federal agencies are expected to add, remove, edit, and/or change in the template language to fit their needs and requirements.