PNNL is supporting the Army’s efforts to provide local, secure energy for military installations using nuclear microreactors.

(Illustration by Stephanie King | Pacific Northwest National Laboratory)

In his twenties, Bruce McDowell listened as his father proposed the idea of building a small hydroelectric power plant on a stream that ran through the family’s property. Unfamiliar with the process but undeterred, McDowell completed the project in four years.

The venture gave him insight into the significance of a local, reliable, and safe power source and how to navigate difficult regulatory and policy hurdles.

Now, decades later, McDowell, an advisor at Pacific Northwest National Laboratory (PNNL), is part of a team, led by Caroline Harrover and Jim Cabe, that is supporting the U.S. Department of the Army’s efforts to provide local, secure energy to military installations through the use of nuclear microreactors.

The Janus Program was launched last year by the Army as its advanced, next-generation nuclear power program, which the PNNL team has supported since its conception. Working with industry and the national laboratories, Janus plans to build commercial microreactors and expedite delivery of advanced energy solutions to American warfighters.

In August, the Army selected five initial locations and five industry partners to build and operate nuclear microreactors.

Identifying solutions for safe, reliable energy

As the largest single user of energy in the United States, the U.S. military regularly looks for solutions that provide reliable, safe energy that enables service members to support America’s national security missions, uninterrupted.

In May of 2025, the White House issued an executive order that directed the Department of War (DOW) and the Department of the Army to evaluate and implement the use of nuclear energy on military installations. It was the launchpad to announce the Janus Program.

McDowell said a nuclear microreactor “can power mission-critical facilities and end uses that require resilient, reliable, and secure energy, or depending on its size, the services necessary for life support during disasters like hurricanes or any situation when the power supply is knocked off the grid.”

In anticipation of the Janus launch, the PNNL team—in support of the Army Reactor Regulatory Office—published a framework for the process, Army Reactor Program Regulatory Bases, and supporting information on nuclear safety, such as radiological dose acceptance and design criteria.

“We wrote a road map that sought to identify gaps in the Army’s capabilities and organizational alignment and directly address challenges associated with technology development, policy and guidance clarification, and maturation of requirements for eventual employment,” said Cabe. “We wanted to provide the Army useful information that could help them evaluate and match the microreactor technologies to the locations and missions that could benefit by a future microreactor.”

A precursor to Janus, Project Pele was launched in 2022 with the goal to design, build, and demonstrate a prototype mobile nuclear reactor. Named after the Hawaiian goddess of fire and volcanoes, Project Pele is led by the DOW Strategic Capabilities Office in collaboration with industry partners and Department of Energy national laboratories.

For Project Pele, the PNNL team was tasked with addressing regulatory challenges. These included testing and acceptance, safe transport, operations, and even potential end-of-life requirements for the prototype microreactor. An added complexity to the project was identifying technically and legally defensible mechanisms to transport a microreactor that contained spent nuclear fuel.

Cabe said it was a unique and well-aligned opportunity for the PNNL team, leveraging decades of experience working with partners such as the Nuclear Regulatory Commission and military services on energy and nuclear power related challenges. One key effort included a first-of-its-kind risk assessment and transportation methodology for a nuclear-fueled reactor that was published in August 2024. It supports the plan that includes the completion of a microreactor at Idaho National Laboratory in 2028 for start-up and operations.

Jumpstarting Janus for transport-capable nuclear power

The Army leveraged a 2025 DOW report that evaluated potential military installations where an advanced nuclear microreactor could be sited and operated and then announced the Janus Program in the fall of 2025. Focusing on key tenets of mission-critical and mission-essential capabilities, the Army completed a comprehensive siting survey and analysis across the continental United States. From that process, nine Army installations were further down selected as prioritized locations to potentially demonstrate the construction and operation of a nuclear microreactor.

After transportation and construction, the microreactors could provide up to 20 megawatts of power to the Army site, with an objective to provide power to critical missions, facilities, and personnel.

Photo provided by the Army
Through projects like Janus, the PNNL team supports Army mission success with service members in mind. (Photograph by Staff Sgt. Christopher Saunders | U.S. Army)

While the Janus Project is focused on installation energy resiliency at Army and other service installations, the success of Janus is expected to have a much longer reach as experts evaluate the potential of a transportable microreactor capability in support of worldwide military operations, said Cabe.

During active conflicts, military convoys carrying diesel fuel can become targets of enemy attacks and have proven vulnerable. McDowell said the use of nuclear microreactors for operational energy may reduce the exposure, minimizing the risk of potential casualties. The potential for accidents has already been significantly reduced due to advancements in robust nuclear fuel and containment designs.

Cabe and McDowell agree that working on the Janus Project has been rewarding because of its focus on protecting—and possibly providing an enduring energy solution for—our service members and the nation’s strategic interests.

“We are highly respectful of our military and the actions they must take,” said Cabe, who has gathered input from hundreds of service members and organizations responsible for production, delivery, and sustainment of energy for the military through the years. “It’s important to talk to the people executing those missions to understand and provide more resilient solutions that help them deliver on their objectives.”

The work is funded by the U.S. Department of the Army.

###

About PNNL

Pacific Northwest National Laboratory draws on its distinguishing strengths in chemistry, Earth sciences, biology and data science to advance scientific knowledge and address challenges in energy resiliency and national security. Founded in 1965, PNNL is operated by Battelle and supported by the Office of Science of the U.S. Department of Energy. The Office of Science is the single largest supporter of basic research in the physical sciences in the United States and is working to address some of the most pressing challenges of our time. For more information, visit the DOE Office of Science website. For more information on PNNL, visit PNNL's News Center. Follow us on LinkedIn, Facebook, YouTube, Instagram and X.