Abstract

A building energy assessment was performed by a team of engineers from Pacific Northwest National Laboratory (PNNL) under contract to the Department of Energy/Federal Energy Management program (FEMP). The effort used the Facility Energy Decision System (FEDS) model to determine how energy is consumed at Hickam AFB, identify the most cost-effective energy retrofit measures, and calculate the potential energy and cost savings. This documents reports the results of that assessment.

Revised: March 19, 2011 | Published: September 30, 2010

Citation

Chvala W.D., M.I. De La Rosa, D.R. Brown, and D.R. Dixon. 2010. Building Energy Audit Report, for Hickam AFB, HI Richland, WA: Pacific Northwest National Laboratory.