May 26, 2006
Report

Sampling and Analysis Plan - Waste Treatment Plant Seismic Boreholes Project

Abstract

This sampling and analysis plan (SAP) describes planned data collection activities for four entry boreholes through the sediment overlying the basalt, up to three new deep rotary boreholes through the basalt and sedimentary interbeds, and one corehole through the basalt and sedimentary interbeds at the Waste Treatment Plant (WTP) site. The SAP will be used in concert with the quality assurance plan for the project to guide the procedure development and data collection activities needed to support borehole drilling, geophysical measurements, and sampling. This SAP identifies the American Society of Testing Materials standards, Hanford Site procedures, and other guidance to be followed for data collection activities.

Revised: June 2, 2006 | Published: May 26, 2006

Citation

Reidel S.P. 2006. Sampling and Analysis Plan - Waste Treatment Plant Seismic Boreholes Project Richland, WA: Pacific Northwest National Laboratory.