This document describes two sets of simulations carried out to further verify and validate the eSTOMP simulator. In this report, a distinction is made between verification and validation, and the focus is on verifying eSTOMP through a series of published benchmarks on cementitious wastes, and validating eSTOMP based on a lysimeter experiment for the glassified waste. These activities are carried out within the context of a scientific view of validation that asserts that models can only be invalidated, and that model validation (and verification) is a subjective assessment.

Revised: November 30, 2016 | Published: May 13, 2016

Citation

Freedman V.L., D.H. Bacon, and Y. Fang. 2016. Integrated Disposal Facility FY 2016: ILAW Verification and Validation of the eSTOMP Simulator Richland, WA: Pacific Northwest National Laboratory.